1.2 Construction Plans and Profiles (CPAP)

Return to Homepage

Construction Plans and Profiles (CPAP)Return For CorrectionReturn For CorrectionESI Minimum Submission Review:
Plan documents are reviewed by an ESI Staff Engineer to determine if all elements are present to warrant a technical review.Plan Intake:
Once found acceptable by ESI review, the plan documents are presented for processing.Engineering Division TL Review:
The Engineering Divison Team Leader conducts a preliminary review of the application package and assigns it to a project manager.Plan Review Referral:
The plan sets are prepared and distributed to the appropriate referral organizations.Schedule ESI Team Peer Review:
The application is scheduled for the ESI Team Peer Review session based on its status as a DPE or nonDPE plan.Technical Plan Review (CPAP):
The plan set is reviewed for conformance with applicable regulations, preliminary plans, special exception applications, and rezoning applications.Technical Plan Review (CPAP):
The plan set is reviewed for conformance with applicable regulations, preliminary plans, special exception applications, and rezoning applications.Comment LTR:
A comment letter is prepared for the applicant listing cited required corrections and recommended plan improvements.Technical Plan Review (CPAP):
The plan set is reviewed for conformance with applicable regulations, preliminary plans, special exception applications, and rezoning applications.Return For CorrectionReturn For CorrectionFSM Waiver:
Applications for waivers to the Facilities Standard Manual are evaluated.Steep Slopes or Mountainside:
Applications for projects on steep slopes or mountainsides are evaluated.Floodplain:
Applications for projects on flood plains are evaluated.Wetlands:
Applications for projects on wetlands are evaluated.Easements:
Applications for easements are evaluated.County Attorney Review:
Issues that may involve a legal interpretation or legal matter are referred to the County Attorney for review.Engineering Issue Resolution:
Issues with projects requiring waivers or construction on steep slopes, mountainsides, floodplains, and/or wetlands are resolved.Grading Permit Application:
The application to obtain approval to conduct land disturbing activity in conjunction with an approved plan is filed.Field Management Team Review:
A technical review of the plan for required erosion and sedimentation controls is conducted.Bond EstimateFull Approval:
The Director grants full approval of the plan.Plan Approval Signature:
The Chief Engineer signs the plan cover sheet as approvedPlan Approval LTR:
An official plan approval letter is prepared.Approved Plan Distribution:
The approved plan documents with the approval letter are distributed.Building/Zoning Permit Application:
The application to obtain approval for a building/zoning permit for an approved plan is filed.Building/Zoning Permit Approval:
A building/zoning permit is issued for the approved plan.Obtain Address(es):
The application to obtain an official address(es)for an approved plan is filed.Overlot Grading Permit Application:
The application to obtain approval for an overlot grading permit for an approved plan is filed.Entrance Permit Application:
The application to obtain approval for an entrance permit for an approved plan is filed.Obtain grading permit:
An approved grading permit must be obtained prior to conducting land disturbing activity.